Funds raised US$450,788,756
Nets funded 217,738,019
People protected 391,928,434

Tanganyika Province, 2023, Congo (Dem. Rep.)  

Summary

Nets: 2,254,000 LLINs
When: Jun 23
Distributed by:  NMCP/Various


2.3 million nets will be distributed in all 11 Health Zones to achieve universal coverage (all sleeping spaces covered) across a population of some 4.1 million people.
Map

Details

 

Donations funding nets     view donations funding non-net costs

We allocate donations individually to specific distributions. This is consistent with being accountable and transparent with the funds we receive. It also allows donors to engage with a net distribution by being able to follow the progress of the nets they have funded. A distribution is typically divided into a series of locations.

Summary

  • 9 donations from 1 donors in 1 countries
  • Smallest donation: US$250,000.00, largest donation: US$500,000
  • (*Figures are 'to date' as funds are still being allocated)

Locations

Click on a location to view the donations that funded it.

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
177,400   Ankoro ZdS, Tanganyika Province Jun 23 Status
220,100   Kabalo ZdS, Tanganyika Province Jun 23 Status
265,350   Kalemie ZdS, Tanganyika Province Jun 23 Status
121,600   Kansimba ZdS, Tanganyika Province Jun 23 Status
136,400   Kiambi ZdS, Tanganyika Province Jun 23 Status
230,100   Kongolo ZdS, Tanganyika Province Jun 23 Status

Survey status

Surveys take place 6, 18, 30 and 42 months post-distribution. A survey of 50 households provides sample information on what proportion of nets continue to be used, if they are used correctly and the state of the nets.

  • Expected
  • Not expected
  • Very good/good
  • Acceptable
  • Not OK
  • Partner Refused
# LLINs LocationWhenStatus
240,150   Manono ZdS, Tanganyika Province Jun 23 Status
145,550   Mbulula ZdS, Tanganyika Province Jun 23 Status
243,100   Moba ZdS, Tanganyika Province Jun 23 Status
261,000   Nyemba ZdS, Tanganyika Province Jun 23 Status
213,250   Nyunzu ZdS, Tanganyika Province Jun 23 Status

Distribution status

The bednet distribution programmes go through a number of different states from being manufactured to being installed over a head/bed:
  • Pre-manufacture
  • Being manufactured
  • Ready at factory
  • En-route to country
  • Arrived in country
  • En-route to zone
  • Being distributed
  • Distribution complete