Tidal Lagoon Swansea Bay

About this project

Tidal lagoon and associated electricity generating infrastructure with a nominal capacity of 240MW.

Visit developer’s website

Recent activity

notice icon

The examination timetable (Rule 8 letter) has been sent to interested parties

Read the letter

Procedural decision following Preliminary Meeting

Documents for Deadline I in relation to the site inspection and the hearings have been published.

The Examining authority have published a notification letter setting out dates, times and locations of hearings and the accompanied site visit.

30 June 2014
notice icon

The applicant’s covering letter and submission in response to s51 advice, dated 4 June 2014, has now been published.

17 June 2014
notice icon
17 June 2014
milestone icon
  • Preliminary Meeting takes place
  • Examination begins
10 June 2014
notice icon

Correspondence submitted during the pre-examination stage and accepted by the Examining Authority, is continuing to be published.

This includes submissions relating to issues which some interested parties wish to be placed on the agenda at the Preliminary Meeting on 10 June 2014.

4 June 2014

What happens next

Notice of the procedural decision has been issued by the Examining authority to interested parties in the Rule 8 letter; this includes information about how the examination will be conducted and the timetable as currently set out.

Dates of the examination can also be viewed on the Examination Timetable page.

If you have a legal interest in land affected by a nationally significant infrastructure project and have not already registered to become an interested party, then you can make a request to the Examining Authority to become an interested party under s102A of the Planning Act 2008 (as amended).