East Northants Resource Management Facility

About this project

The alteration of existing and the construction of new facilities for the recovery and disposal of hazardous waste and disposal of low level radioactive waste at the East Northants Resource Management Facility, Stamford Road, Northamptonshire.

Visit developer’s website

Recent activity

milestone icon
Decision made by the Secretary of State
11 July 2013
notice icon

The Examining Authority has issued its recommendation to the Secretary of State. A decision will be published on or before 22 July 2013. Please note that the Examining Authority’s recommendation will also be made available at that point.

22 April 2013
milestone icon
Recommendations given by the Planning Inspectorate
22 April 2013
notice icon

The Examining Authority has issued a letter under section 99 of the Planning Act 2008 (as amended) notifying Interested Parties of the completion of the examination. There will now be a period of 3 months for the Examining Authority to consider and make a recommendation to the Secretary of State.

23 January 2013

What happens next

A decision on the application for a development consent order for East Northants Resource Management Facility was taken on 11 July 2013 and has now been issued. The statement of reasons can be viewed here.

The period for legal challenge is defined in s118 of the Planning Act 2008. Further information about legal challenge can be found in the letter sent to all interested parties accompanying the statement of reasons.

If you have any queries about the process please email the Planning Inspectorate at enquiries@infrastructure.gsi.gov.uk or telephone the helpdesk on 0303 444 5000.