About this project
Offshore wind farm with a generating capacity of 700MW together with offshore and onshore electrical infrastructure including cable route from the coast to a new substation near the existing Bolney Substation in Mid Sussex.Recent activity
The Examining Authority issued its recommendation to the Secretary of State on 17 April 2014. A decision will be published within 3 months. Please note that the Examining Authority’s recommendation will also be made available at that point.
A letter notifying parties of further published documents is available.
The examination has closed. There will now be a period of 3 months for the Examining Authority to consider and make a recommendation to the Secretary of State.
The Examining Authority has issued a request for further information in accordance with Rule 17 of the Infrastructure Planning (Examination Procedure) Rules 2010.
What happens next
The Planning Inspectorate issued a report of recommendation to the Secretary of State on 17 April 2014. The Secretary of State has 3 months in which to issue a decision. The decision letter and report of recommendation will be published on this page of the website once a decision has been made.