Knottingley Power Project

About this project

A 1500 MW Combined Cycle Gas Turbine (CCGT) power station and associated infrastructure.

Visit developer’s website

Recent activity

notice icon

The submissions for the deadline of 20 June 2014 have now been published including responses to the ExA’s second round of written questions and comments on written summaries of cases put at any issue specific hearings. In addition following submissions were received:
Revised application documents submitted by the Applicant including draft DCO
Updates on agreements and Statements of Common Ground

24 June 2014

What happens next

Notice of the procedural decision has been issued by the Examining authority to interested parties in the Rule 8 letter; this includes information about how the examination will be conducted and the timetable as currently set out.

Dates of the examination can also be viewed on the Examination Timetable page.

If you have a legal interest in land affected by a nationally significant infrastructure project and have not already registered to become an interested party, then you can make a request to the Examining Authority to become an interested party under s102A of the Planning Act 2008 (as amended).