Proposed Burbo Bank Extension offshore wind farm covering an area of 40 km² and with an estimated generating capacity of up to 250 MW. The proposed project would be located west of the operational Burbo Bank offshore wind farm in Liverpool Bay, around 7 km north of the North Wirral coast, 8.5 km from Crosby beach, and 12.2 km from the Point of Ayr on the Welsh coast

Visit developer’s website

Recent activity

notice icon

The Examining Authority issued its recommendation to the Secretary of State on 26 June 2014. A decision will be published within 3 months. Please note that the Examining Authority’s recommendation will also be made available at that point.

27 June 2014
milestone icon
Recommendations given by the Planning Inspectorate
26 June 2014
notice icon

The examination has now closed. There will now be a period of 3 months for the Examining Authority to consider and make a recommendation to the Secretary of State. Please see the letter sent to Interested Parties.

Responses to Deadline VII, prior to the close of examination, have now been published.

27 March 2014
milestone icon
Examination ends
26 March 2014
notice icon

Responses to Deadline VI have now been published.

14 March 2014

What happens next

The Planning Inspectorate issued a report of recommendation to the Secretary of State on 26 June 2014. The Secretary of State has 3 months in which to issue a decision. The decision letter and report of recommendation will be published on this page of the website once a decision has been made.