M1 Junction 10a Grade Separation proposes to upgrade Junction 10A from the existing at grade roundabout to a grade separated junction.

Visit developer’s website

Recent activity

notice icon

The Secretary of State has granted development consent for this application. For further information, please refer to the following decision documentation:

Secretary of State Decision Letter
Development Consent Order as made by the Secretary of State
Examining Authority’s report to the Secretary of State
Planning Inspectorate notification of decision letter

30 October 2013
milestone icon
Decision made by the Secretary of State
30 October 2013
notice icon

The Examining Authority has issued its recommendation to the Secretary of State. A decision will be published on or before 13 November 2013. Please note that the Examining Authority’s recommendation will also be made available at that point.

13 August 2013
milestone icon
Recommendations given by the Planning Inspectorate
13 August 2013
notice icon

The Examining Authority has issued a letter under section 99 of the Planning Act 2008 (as ammended) notifying Interested Parties of the completion of the examination. There will now be a period of 3 months for the Examining Authority to consider and make a recommendation to the Secretary of State.

13 May 2013

What happens next

A decision on the application for a development consent order for M1 Junction 10a Grade Separation - Luton was taken on 30 October 2013 and has now been issued. The statement of reasons can be viewed here.

The period for legal challenge is defined in s118 of the Planning Act 2008. Further information about legal challenge can be found in the letter sent to all interested parties accompanying the statement of reasons.