Thorpe Marsh Gas Pipeline

About this project

The Proposed Gas Pipeline will be a continuously welded buried steel pipeline of approximately 18 km in length from an offtake approximately 1.5 km west of Camblesforth to the Thorpe Marsh CCGT Power Station site. It will include the following elements:

· A Minimum Off-take Connection (MOC) to the National Transmission System (NTS) – to be constructed and operated by the National Grid;

· Offtake Above Ground Installation (AGI), adjacent to the National Grid offtake, which will contain pipeline control valves and Pipeline Internal Gauging (PIG) ‘pigging’ facilities;

· A cross-country pipeline between the offtake AGI and the proposed CCGT Power Station; and

· A Gas Reception Facility (GRF) at the power station within the power station site which will contain pipeline control valves and pipeline pigging facilities. N.B. the GRF has existing planning consent under the Electricity Act 1989 Section 36 as it is within the power station "Red Line" development area.

What happens next

The application is expected to be submitted to the Planning Inspectorate Q3 2014.

After receipt of the application, there will be 28 days to review the application and decide whether or not to accept it.

If the application is accepted, we will advise the timescales when interested parties can register to make a representation.

If the application is accepted, we will:

  • Publish all the application documents on this project page
  • Publish the date from which you will be able to register to put your case on the application
  • Publish the date on which registration will close.